CHAPTER SEVEN : STANDARD COSTING
What is Standard Costing :
Standard costing is a technique which establishes predetermined
estimates of the costs of products and services and then compares these
predetermined costs with actual costs as they are incurred.
The predetermined costs are known as standard costs and the difference between the standard cost and
actual is known as a variance.
The process by which the total difference between actual cost and
standard cost is broken down into its different elements is known as variance analysis.
Definition of Standard Cost :
A standard cost is a standard expressed in money. It is a target cost
which should be attained.
Uses of Standard Costing
Standard costing has two principal uses:
-
To act
as a control device via variance analysis.
-
To value
stocks and cost production.
Types of Standards
There are three types of standard; basic, ideal and attainable.
i)
Basic standards: These are long term standards which would remain unchanged over
the years. Their sole role is to show trends over time for such items as
material prices, labour rates and efficiency
and the effect of changing methods. They cannot be used to highlight
current efficiency or inefficiency and would not normally form part of the
reporting except as a background, statistical exercise.
ii)
Ideal Standards : These are based on the best possible
operating conditions, i.e no breakdowns,
no material wastage , no stoppage or idle time , in short, perfect efficiency.
iii)
Attainable standard : This is by far the most frequently
encountered standard. It is a standard based on efficient ( but not perfect )
operating conditions. The standard would
include allowances for normal material losses, realize allowance for fatigue, machine breakdowns etc
.
Setting
Standards
Setting standards is detailed, lengthy
process usually based on engineering and technical studies of times, materials
and methods. Standards are set for each of the elements which make up the
standard cost: materials, labour and overheads.
The following lines explain some of the
detailed procedures involved in setting
standards.
Setting
Standards – material price
v Estimated by purchasing department
v Problems:
Ø Allowing for bulk purchase discounts
Ø Allowing for inflation
- Current price (procedures constantly
increasing adverse variances)
- Estimated mid-year price (procedures
favourable variances in the first half of the year, adverse variance in the
second half)
Setting Standards – Labour rate
v Set by reference to the payroll, taking
account of any agreed pay rises.
v (Average) rate for each grade / type of
employee
v Problem of wage rate inflation
Setting
Standards – Material usage and Labour efficiency
v Technical specifications prepared for each
product by production experts.
Setting Standards – Overheads
v Standard absorption rate = predetermined OAR
v Standard absorption rate depends on planned
production volume, which depends on two factors
Ø Production capacity (in standard hours of
output)
Ø Efficiency of working
Setting Standards – Sales
Standard selling price will depend on a number of factors.
v Anticipated market demand
v Manufacturing cost
v Competition
v Inflation
Variance Analysis
A variance is the difference between an actual result and an expected
result.
When actual results are better than expected results, we have a
favourable variance (F) but if actual results are worsen than expected results,
we have an adverse variance (A).
The following information will
be used throughout our discussion below:
Standard cost of Product A
|
GMD
|
Materials ( 5Kg x GMD10 per kg)
|
50
|
Labour (4 hrs x GMD5 per hr)
|
20
|
Variance overheads ( 4 hrs x GMD2 per hr)
|
8
|
Fixed overheads ( 4 hrs x GMD6 per hr)
|
24
|
|
102
|
|
|
Budgeted results
|
Results
for July 2010
|
Production: 1,200
|
Production: 1,000
units
|
Sales : 1,000 units
|
Sales: 900 units
|
Selling price: GMD150 per unit
|
Materials: 4,850
kgs, GMD46,075
|
|
Labour: 4,200 hrs,
GMD21,210
|
|
Variable
overheads: GMD9,450
|
|
Fixed overheads: GMD25,000
|
|
Selling price: GMD140
per unit
|
Direct Material Variances
This is the difference between what the output actually cost and what
it should have cost, in terms of material.
|
GMD
|
1,000 units should have cost (x GMD50)
|
50,000
|
But did cost
|
46,075
|
Direct material total variance
|
3,925
(F)
|
It can be divided into two sub-variance as follows:
v The
direct material price variance
: This is the difference between what the actual quantity of material used did
cost and what it should have cost.
|
GMD
|
4,850 kgs should have cost (x GMD10)
|
48,500
|
But did cost
|
46,075
|
Direct material price variance
|
2,425
(F)
|
Reasons for Material Price
Variance:
ü (F) – unforeseen discounts received, greater
care taken in purchasing, change in material standard.
ü (A) – price increase, careless purchasing,
change in material standard.
.
v The direct material usage variance : This is
the difference between how much material should have been used for the number
of units actually produced and how much material was used, valued at standard cost.
|
|
1,000 units should have used (x 5 kgs)
|
5,000 kgs
|
But did used
|
4,850 kgs
|
Variance in kgs
|
150
kgs (F)
|
x standard cost per kg
|
x
GMD10
|
|
GMD1,500
(F)
|
Reasons for Material Usage variance:
ü (F) – material used higher quality than
standard, more effective used made of material.
ü (A) – defective material, excessive waste,
theft, stricter quality control.
Direct Labour Variances
This is the difference between what the output should have cost and
what it did cost, in terms of labour.
|
GMD
|
1,000 units should have cost (x GMD20)
|
20,000
|
But did cost
|
21,210
|
Direct labour total variance
|
1,210
(A)
|
The direct labour variance is sub-divided into two as follows:
v The
direct labour rate variance
: This is the difference between what the actual number of hours paid for did
cost and what they should have cost.
|
GMD
|
4,200 hrs should have cost (x GMD5)
|
21,000
|
But did cost
|
21,210
|
Direct labour rate variance
|
210(A)
|
Reasons for Labour Rate
Variance:
ü (F) – use of workers at rate of pay lower
than standard.
ü (A) – wage rate increase.
v The
direct labour efficiency variance : This is the difference between how many hours should have been
worked for the number of units actually produced and how many hours were
worked, valued at the standard rate per hour.
1,000 units should have taken (x 4 hrs)
|
4,000 hrs
|
But did take
|
4,200 hrs
|
Variance in hrs
|
200 hrs (A)
|
x standard rate per hour
|
x GMD5
|
Direct material price variance
|
GMD1,000 (A)
|
Reasons for Labour Efficiency
Variance:
ü (F) – output produced more quickly than
expected because of work motivation, better quality of equipment or materials..
ü (A) – lost time in excess of standard allowed,
output lower than standard set because of deliberate restriction, lack of
training, sub-standard material used..
Sales Variances
This is sub-divided into two as follows:
v The
selling price variance: This
is the difference between what the sales revenue should have been for the
actual quantity sold, and what it was.
|
GMD
|
Revenue from 900 units should have been (x GMD150)
|
135,000
|
But was
|
126,000
|
Selling price variance
|
9,000(A)
|
v
The
volume variance : This is the difference between what the actual units sold
and the budgeted quantity, valued at the standard profit per unit. It measures
the increase or decrease in standard profit as a result of the sales volume
being higher or lower than budgeted.
Budgeted sales volume
|
1,000 units
|
Actual sales volume
|
900 units
|
Variance in units
|
100 units (A)
|
x standard margin per
unit ( x GMD150 - GMD102)
|
x GMD48
|
Direct material price variance
|
GMD4,800
(A)
|
PRACTICE
QUESTIONS
1. The
standard cost of making one unit is as follows:
Direct
material 4 kilos
at GMD7 per kilo
Direct
wages 5 hours at
GMD12 per hour
The
actual cost of a batch of 100 units was:
Direct
material GMD2,920
(435 kilos)
Direct
wages GMD6,250
(480 hours)
REQUIRED
a) Calculate the following:
i the material price variance [2]
ii the material usage variance [2]
iii the total material cost variance [1]
iv the labour rate variance [2]
v the labour efficiency variance [2]
vi the total labour cost variance [1]
vii the total cost variance [2]
b) Outline possible causes of the variances. [4]
2. The standard cost of making one unit is
as follows:
Direct
material 7 kilos at GMD8.20
per kilo
Direct
wages 6 hours at GMD9 per
hour
The
actual cost of a batch of 100 units was:
Direct
material GMD6,102 (795
kilos)
Direct
wages GMD5,740 (580
hours)
REQUIRED
a) Calculate the following:
i the material price variance [2]
ii the material usage variance [2]
iii the total material cost variance [1]
iv the labour rate variance [2]
v the labour efficiency variance [2]
vi the total labour cost variance [1]
vii the total cost variance [2]
b) Outline possible causes of the variances. [4]
c) Distinguish between a budget and a standard. [4]
3. The
standard cost of making one unit is as follows:
Direct
material 3 kilos at GMD4 per kilo
Direct
wages 2 hours at GMD8 per hour
The
actual cost of a batch of 500 units was:
Direct
material GMD6,570 (1,680 kilos)
Direct
wages GMD8,250 (975 hours)
REQUIRED
a) Calculate the following:
i the material price variance
ii the material usage variance
iii the labour rate variance
iv the labour efficiency variance [3 each]
b) Outline possible causes of the
variances. [4]
c) Explain the major purposes of standard (4)
No comments:
Post a Comment